PART - B Max Mark: 30Marks

Answer the following (2x15=30Marks)

  1. 1.a)

    Using graphical method, solve the rectangular game whose payoff matrix for player A is

    B1B2B3B4
    A1104-1
    A2-11-25
    15mCO3BL2
    OR
  2. b)

    Solve the following game whose pay off matrix is

    Player A \ Player BIIIIIIIV
    I-53120
    II5546
    III-4-20-5
    15mCO3BL2
  3. 2.a)

    i. Draw the Network for the Project given below. (5 MARKS)
    Activities: A, D, E can start simultaneously
    Activities: B, C > A ; G, F > D, C ; H > E, F

    ii. Draw the network and determine the critical path for the given data. Also find the free float, total float, Independent float of each activity (10 MARKS)

    Jobs1-21-32-43-43-54-54-65-6
    Duration651034629
    15mCO4BL2
    OR
  4. b)

    The following table list the jobs of a network along with their time estimates

    Jobs1-21-32-43-44-53-5
    Optimistic time295268
    Most likely time512145617
    Pessimistic time14151781220

    i. Calculate length and variance of the critical path.
    ii. Find the probability that the project will be completed with in 30 days

    15mCO4BL2